As of 07-26-2019 the following work is being performed:

In the past week construction installed 120 feet of pipe from manhole #14 to #15 and they are digging to install another 150 feet of pipe and set manhole #16 today. They installed lateral tees for the reaming Shady Brook Circle homes and installed lateral tees for 165 & 184 Pebble Ridge Road. Minor rock was encountered about 1-2 feet above invert (bottom of trench). This was a short week due to delivery and First Aid / CPR Training. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.

In the next week weather permitting we will expect to install:

  • Continue the approx. 1000 linear feet of sewer main up to manhole (#17) on Pebble Ridge Road
  • Manhole #17
  • The lateral connection stubs for residents at 191, 203, 206 Pebble Ridge Road
  • Continue meeting with residents to identify lateral location and depth