In the past week construction installed approximately 430 feet of pipe from Manhole #15 to just short of MH #17 and they are digging to install another 70 feet of pipe and set Manhole #17 today. They installed lateral tee for 191 Pebble Ridge Road.  Rock was encountered about 1-2 feet above invert (bottom of trench).  Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.

In the next 2 weeks weather permitting we will expect to install:

  • Continue the approximately 1000 linear feet of sewer main up to manhole (#20) on Pebble Ridge Road to complete that leg of the sewer
  • Manholes #18, #19,#20
  • The lateral connection stubs for residents at 203, 206 Pebble Ridge Road, 487 Pebble Crest and, if rock is mild, additional lateral tees as we progress up Pebble Ridge Road