Pebble Ridge Sewer Project Update – August 09, 2019

In the past week construction installed approximately 100 feet of pipe from Manhole MH #17 on Pebble Ridge Road. They installed lateral tees for 487 Pebble Crest, 203, 206, and 215 Pebble Ridge Road.  Rock was encountered about 1-2 feet above invert (bottom of trench). Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Letters to the residents who will have lateral tees set in the next 2-4 weeks were sent out on August 9, 2019.

In the next 2 weeks weather permitting we will expect to install:

  • Continue the approximately 900 linear feet of sewer main up to manhole (#20) on Pebble Ridge Road to complete that leg of the sewer
  • Manholes #18, #19,#20
  • The lateral connection stubs for residents at 218, 227, 230 Pebble Ridge Road, if rock is mild, additional lateral tees as we progress up Pebble Ridge road
  • Continue meeting with residents to identify lateral location and depth