Pebble Ridge Sewer Project Update – December 31, 2019

70 LF of pipe was installed on Stony Lane. Test pits for rock depth completed on Woodridge and Westaway show additional drilling is needed. Significant rock at the bottom of the drilled area on Stony Lane and significant water in the trench off Lower State Road has slowed production. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of Stony Lane is completed.

In the next week weather and conditions permitting we will expect to install:

  • 100 LF of pipe on Stony Lane Road
  • Manhole #30 on Stony Lane Road
  • Continue meeting with residents to identify lateral location and depth
  • Due to the short holiday week we will only have one crew who will continue the installation of sewer on Stony Hill Road