Pebble Ridge Sewer Project Update – February 19, 2021

We installed 24 LF of pipe towards MH#9.  The second crew installed 14 LF of pipe towards MH#38 on Springdale.  We are hitting a tremendous amount of rock and groundwater.  Soil sampling for new dump sites was conducted and manhole sealing was also performed.

 

A special note for the residents of Willow

Residents on Willow will not be able to hook up to the sewer until the lower part of the easement line is completed over the next few months.

 

In the next week weather and conditions permitting we will expect to install:

  • Continue installing pipe in the easement from Old New Road towards the Lower State Road easement section from MH#8 to MH#9
  • Continue installing main on Springdale towards MH#38
  • We are continuing to identify additional dump sites that we can utilize for the excavated material
  • Sweeping and cold patching where needed

 


BCWSA Employees will be putting safety protocols for the Corona virus in place on the job site.  They will be wearing gloves, keeping distance between each other when possible & as appropriate, wiping down equipment & vehicles while in use.  Interaction with residents is to be postponed.  If a lateral location needs to be adjusted any interaction between residents and BCWSA personnel will be done with the appropriate social distancing & protection needed for safety.