Pebble Ridge Sewer Project Update – January 28, 2020

192LF of pipe was installed on Woodridge and in the easement off Lower State Road.  We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench on the easement off Lower State Road.  Test pits for rock depth in other areas will be completed in the next two weeks.  Drilling on Westaway is continuing.  Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.

In the next week weather and conditions permitting we will expect to install:

  • 100 Lf of sewer main Woodridge and MH#31
  • 100 LF of force main and MH PS-4 and sewer and force main to MH PS-5 in the easement between Lower State Road and Old New Road
  • Test pits for soil samples in areas yet excavated will be performed
  • Continue meeting with residents to identify lateral location and depth
  • Saw Cutting on Woodridge and Westaway will continue
  • Drilling on Westaway will continue