Pebble Ridge Sewer Project Update – June 04, 2021

We installed 80LF of pipe and MH#13 on the easement off Old New Road.  The second crew installed 224LF of pipe towards MH#85 in David’s Way.  Drilling in Old New Road is continuing.

 

A special note for the residents of Willow

Residents on Willow will not be able to hook up to the sewer until the lower part of the easement line is completed over the next few months.

 

In the next week weather and conditions permitting we will expect to install:

  • Continue installing main on David’s Way to MH#85
  • Continue installing main work on the upper easement between Lower State Road and Old New Road towards the MH in Old New Road
  • Drilling in Old New Road
  • Sweeping and cold patching where needed

 


BCWSA Employees will be putting safety protocols for the Corona virus in place on the job site.  They will be wearing gloves, keeping distance between each other when possible & as appropriate, wiping down equipment & vehicles while in use.  Interaction with residents is to be postponed.  If a lateral location needs to be adjusted any interaction between residents and BCWSA personnel will be done with the appropriate social distancing & protection needed for safety.