We will be closing Old New Road from Westaway to David’s way starting on Monday.

 

We installed 320LF of pipe and MH#50 in Old New Road. The second crew installed 14LF of main heading towards MH#52 in Old New Road. Restoration of the easement off Willow Lane and off Old New Road.

 

A special note for the residents of Willow

Residents on Willow will not be able to hook up to the sewer until the lower part of the easement line is completed over the next few months.

 

In the next week weather and conditions permitting we will expect to install:

  • Crew #1 will continue installing main in Old New Road from MH#14 towards Westaway Lane
  • Crew #2 will continue installing main in Old New Road from MN#14 towards David’s Way
  • Drilling in Old New Road
  • Sweeping and cold patching where needed

 


BCWSA Employees will be putting safety protocols for the Corona virus in place on the job site.  They will be wearing gloves, keeping distance between each other when possible & as appropriate, wiping down equipment & vehicles while in use.  Interaction with residents is to be postponed.  If a lateral location needs to be adjusted any interaction between residents and BCWSA personnel will be done with the appropriate social distancing & protection needed for safety.