Pebble Ridge Sewer Project Update – March 20, 2020

The crew installed 180 LF of main and MH#40 on Stony Lane Circle.  100 LF of force main and sewer main was installed into MH#7 and main into MH#PS 15.  We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench on the easement off Lower State Road.  Drilling on Westaway is continuing.  Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.

DUE TO THE GOVERNORS DIRECTIVE THE PROJECT HAS BEEN SHUT DOWN UNTIL FURTHER NOTICE STARTING MONDAY 3-23-20.