Pebble Ridge Sewer Project Update – November 06, 2020

We installed 2 laterals on Old New Road and 238LF of sewer main and MH#27 on Buck Road from Old New Road. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing. The project is currently on budget but behind schedule about 9 weeks.

A special note for the residents of Willow

Residents on Willow will not be able to hook up to the sewer until the lower part of the easement line is completed over the next few months.

 

In the next week weather and conditions permitting we will expect to install:

  • Install sewer main on Buck Road from MH# 27 to MH#28
  • Sweeping and cold patching of Buck Road

 


BCWSA Employees will be putting safety protocols for the Corona virus in place on the job site.  They will be wearing gloves, keeping distance between each other when possible & as appropriate, wiping down equipment & vehicles while in use.  Interaction with residents is to be postponed.  If a lateral location needs to be adjusted any interaction between residents and BCWSA personnel will be done with the appropriate social distancing & protection needed for safety.