Pebble Ridge Sewer Project Update – November 15, 2019

In the past week construction installed 140 LF of pipe on Stony Lane.  Significant rock at the bottom of the drilled slowed production.  Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of Stony Lane is continuing.  Paving is scheduled for the 19th on Pebble Ridge Road.

In the next week weather and conditions permitting we will expect to install:

  • Sewer Main and Force Main installation will continue from Lower State road in the easement area off of Old New Road
  • 150 LF of pipe on Stony Lane
  • Manhole #29 on Stony Lane
  • The driller is continuing to pre-drill Stony Lane
  • Continue meeting with residents to identify lateral location and depth
  • Milling and paving of portions of Pebble Ridge Road are expected to begin weather permitting by 11-19-19 at the latest
  • One crew will continue the installation of gravity main and force main in Lower State Road and the 2nd crew will install sewer on Stony Hill road