Pebble Ridge Sewer Project Update – September 04, 2020

The crew installed 226LF of sewer main and 230LF of force main on Westaway. The crew installed 394LF of sewer main on Willow. Main installation on Willow towards Woodridge is completed. Drilling on Willow near Westaway is continuing. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing. The project is currently on budget but behind schedule about 9 weeks.

A special note for the residents of Willow

Residents on Willow will not be able to hook up to the sewer until the lower part of the easement line is completed over the next few months.

 

In the next week weather and conditions permitting we will expect to install:

  • Continue working up Westaway installing sewer and force main from MH#45 and install MH#46. Continue force main to Woodridge
  • Continue working on Willow. Install Laterals in the areas where the main is completed to allow for water main work to begin
  • Continue meeting with residents (applying social distancing) to identify lateral location and depth
  • Drilling on Willow Lane

 


BCWSA Employees will be putting safety protocols for the Corona virus in place on the job site.  They will be wearing gloves, keeping distance between each other when possible & as appropriate, wiping down equipment & vehicles while in use.  Interaction with residents is to be postponed.  If a lateral location needs to be adjusted any interaction between residents and BCWSA personnel will be done with the appropriate social distancing & protection needed for safety.