• pay bills
  • FOG alert
    fats, oils + grease
  • Emergency Contact
  • Home
  • Help Center
  • For The Public
  • Sales + Refinancing
  • Location + Contact
  • Business Partners
  • How Do We Rate?
  • Open Records
  • About Us

Press Releases

Pebble Ridge Sewer Project Update – April 09, 2021

We completed the install of all laterals on Springdale Road. We installed 477 LF of sewer main and MH#36 on Anvil Lane. We installed 28 LF from MH#8 on the easement off Old New Road. Drilling in the easement off …

Click Here to Read the Rest...


Pebble Ridge Sewer Project Update – April 02, 2021

We installed four (4) laterals on Springdale and drilling in the easement off Old New Road is continuing.

 

A special note for the residents of Willow

Residents on Willow will not be able to hook up to the sewer …

Click Here to Read the Rest...


2021 Spring Hydrant Flushing Schedule

BCWSA will be completing the flushing of the following distribution systems:

 

LOWER SOUTHAMPTON TOWNSHIP
April 12, 2021 through April 16, 2021
April 19, 2021 through April 23, 2021
April 26, 2021 through April 30, 2021

MIDDLETOWN TOWNSHIP
May 3, …

Click Here to Read the Rest...


Pebble Ridge Sewer Project Update – March 12, 2021

We installed the remaining on Buck Road. We began installing laterals on Old New Road.  Lawn restoration was started on the lateral dig ups on Buck road.  Cold patch and trench restoration was also performed on portions of Buck and …

Click Here to Read the Rest...


Pebble Ridge Sewer Project Update – March 05, 2021

We installed 12 laterals on Buck Road. We performed test pit excavation in the easement of Old New Road for potential drilling due to rock.  We are hitting a tremendous amount of rock and groundwater. Cold patch and trench restoration …

Click Here to Read the Rest...


Pebble Ridge Sewer Project Update – February 26, 2021

We installed 28 LF of pipe towards MH#9. The second crew installed 154 LF of pipe on Springdale towards MH#38 on Springdale. We are hitting a tremendous amount of rock and groundwater.

 

A special note for the residents of

…

Click Here to Read the Rest...


Pebble Ridge Sewer Project Update – February 19, 2021

We installed 24 LF of pipe towards MH#9.  The second crew installed 14 LF of pipe towards MH#38 on Springdale.  We are hitting a tremendous amount of rock and groundwater.  Soil sampling for new dump sites was conducted and manhole …

Click Here to Read the Rest...


Pebble Ridge Sewer Project Update – February 12, 2021

We installed 84 LF of pipe and MH#35 to complete the main on Buck. we installed 55 LF of pipe on Springdale towards MH#38 on Springdale. The second crew installed 70 LF in the Old New Road easement towards MH#9.…

Click Here to Read the Rest...


Plumbers & Contractors Access to Authority Facilities

Bucks County Water and Sewer Authority (BCWSA) has adopted regulations establishing requirements for all plumbers and contractors that connect or expose any BCWSA water and/or sanitary sewer facilities when performing work on private public water and public sewer lines that …

Click Here to Read the Rest...


Pebble Ridge Sewer Project Update – February 05, 2021

Due to the storm the dump sites where shut down so no work other than prepping for next week was completed

 

A special note for the residents of Willow

Residents on Willow will not be able to hook up …

Click Here to Read the Rest...


Posts navigation

← Older entries

Categories

  • Environmental Stewardship
  • Hydrant Flushing
  • IPP Customers
  • Pebble Ridge
  • Press Releases
  • Video Clips